12 Mobile Substations – 11.5/230 kV, 20 MVA
Supervision over erection, testing, commissioning and energization of twelve 11.5/230 kV mobile substations (20 MVA).
2013
Algeria
United Company for Electrical Projects (UCEP)
ALSTOM Grid SWEA (Main) + Al-Samama Trading Group Co. (Sub)
The Ministry of Electricity / Electrical Transmission Project (ETP)