Extension of Deir Ali Substation (2012)

Commissioning job for Protection & DCS systems

Scope & Outcome

700 MW Combined Cycle Power Plant 400/230 kV Substations extension in Damascus. Commissioning scope covered protection & DCS systems.

Project Info

Execution Date

2012

Location

Damascus – Syria

Contractor

United Company for Electrical Projects (UCEP)

Client

METKA (Main) + ALSTOM (Sub)

Owner

PEEG – Public Establishment of Electricity for Generation

Deliverables

  • Protection & DCS commissioning
  • Database updates & tests
  • Issue resolution & handover