Calabar (2016)

DSC Testing & Commissioning – 33 kV Substation

Scope & Outcome

Testing and commissioning of Digital Substation Control for 33 kV substation equipment, with database adjustments and integration support.

Resolved outstanding punch-list items for the wider 330/132/33 kV substation and validated protection/control interfaces.

Project Info

Execution Date

2016

Location

Nigeria

Contractor

United Company for Electrical Projects (UCEP)

Client

Marubeni (Main) + ALSTOM Grid UK Ltd – PCS (Sub)

Owner

Ministry of Electricity

Deliverables

  • Testing
  • commissioning
  • issues closure
  • database modifications