DS-Agile Substation Control System – 400/132 kV (10×125 MW 9E GT)

Scope & Outcome

Testing, commissioning and energization of DS-Agile Substation Control System for Al-Khirat Power Plant (400/132 kV, 10×125 MW 9E gas turbines).

Project Info

Execution Date

2013

Location

Iraq

Contractor

United Company for Electrical Projects (UCEP)

Client

Calik Energy (Main) + ALSTOM Grid SAS Iraq Branch (Sub)

Owner

Ministry of Electricity in Iraq

Deliverables

  • Testing
  • commissioning
  • energization of DS-Agile SCS