Project Overview
Complete rehabilitation and modernization of the Homs central 132-kilovolt substation damaged during conflict.
Scope of Work
- Engineering and detailed design under Rabbat Electric LLC technical supervision.
- Procurement of equipment from partnered manufacturers (GE, AREVA, ALSTOM, Siemens) as required by 132 kilovolt class.
- Civil works, installation, and on-site assembly.
- Testing, commissioning, and handover to the client.
Deliverables
- Fully commissioned rehabilitation solution rated 132 kilovolt.
- As-built drawings and operation & maintenance documentation.
- Operator training and post-handover support.