Aleppo Industrial Zone Substation

Turnkey delivery of a medium-voltage substation for the Aleppo industrial zone, powering manufacturing facilities.

Category
Turnkey Contracting
Voltage
66 kilovolt
Location
Aleppo, Syria
Year
2020

Project Overview

Turnkey delivery of a medium-voltage substation for the Aleppo industrial zone, powering manufacturing facilities.

Scope of Work

  • Engineering and detailed design under Rabbat Electric LLC technical supervision.
  • Procurement of equipment from partnered manufacturers (GE, AREVA, ALSTOM, Siemens) as required by 66 kilovolt class.
  • Civil works, installation, and on-site assembly.
  • Testing, commissioning, and handover to the client.

Deliverables

  • Fully commissioned turnkey contracting solution rated 66 kilovolt.
  • As-built drawings and operation & maintenance documentation.
  • Operator training and post-handover support.